Repowering of biomass boiler in a chemical factory.

biomass boiler on industrial plant

W.T.E. delivered basic and detailed engineering to upgrade an existing biomass boiler with 57 MWt at MCR and to build a new thermal cycle with a turbo-generator 14.5 MWe capacity.

The project included also the revamping engineering of the existing boiler with the installation of a new superheater, able to deliver higher steam temperature, the extension of the existing economizer and a new combustion control system.  All these systems and auxiliaries had to be connected to the existing chemical factory.

 

 

CLIENT

INDUNOR- Silvateam Group

LOCATION

La Escondida (Chaco)

COUNTRY

Argentina

YEAR

2018

INDUSTRY

Biomass to Energy plant, General industry

OBJECT

Complete System

ACTIVITY

Basic & Detailed engineeringProcurement services

ASSIGNMENTS

Basic Engineering
Detailed Engineering
Procurement: Support