Activity: Consulting

construction supervision

Consulting about boiler malfunctioning failures

An Italian Joint venture delivered an ORC energy recovery system in the revamping project of an existing  waste incineration plant. Some major problems were recorded after the start up. W.T.E. was required to evaluate the solution proposed by JV in order to avoid litigation with their Client.      

Consulting about malfunctioning

Terni Biomassa Srl commissioned the analysis of the combustion process to W.T.E. in order to verify the capacity of the boiler fed by RDF.

Flue gas cleaning system dimensioning

Engineering services

W.T.E. provided  engineering services to Redecam Group in the project of a new Flue Gas Cleaning System – dry type

low-temperature econimiser

Consulting

ECOSESTO Spa requested W.T.E. to give technical consulting concerning the calculation of feed in tariff after the start-up of the solar plant installed as an auxiliary sytem  of the thermal cycle on the biomass plant in Rende (Calabria).  

Consulting on operational procedures

W.T.E. updated all operational procedures, start-up, emergency shutdown procedures, etc. for each section of the Geofor Spa Incineration plant -Ospedaletto (Pisa).

Consulting on energy self consumption of textile industry

MASCIONI SPA, manufacturer of textile products, requested W.T.E. the analysis about the power self-consumption of a proprietary cogeneration power plant. The report was needed in the context of the negotiation with GSE concerning incentives (feed-in tariff) about renewable sources.

Generation and capture of furans and dioxins in steell mill

ALSTOM Power Italia SpA commissioned to W.T.E. an analysis about dioxin and furan, generated during the melting process into the steel mill electric arc furnace (EAF). The study was integrated by a preliminary project of different abatement plant sections.