Prefeasibility of the conversion of 2 EfW furnaces from fluidized bed to moving grate

Pre-feasibility study of the convertion of the combustion system installed on the incineration plant from owned by Veolia Servizi Ambientali Tecnitalia Spa in Gioia Tauro (RC).

The existing fluid bed furnaces were fed with RDF and they would be transformed into moving grate furnaces fed with MSW. The capacity of the plant was 49 MWth.

W.T.E. delivered the study including the description of all modifications to be realised on the main sections of the plant.

CLIENT

VEOLIA S.A.Tecnitalia Spa

LOCATION

La Spezia

COUNTRY

Italy

YEAR

2009

INDUSTRY

Waste to energy plant

OBJECT

FurnaceBoiler

ACTIVITY

Pre-feasibility study

ASSIGNMENTS

Pre-feasibility study