Feasibility Study of new waste to energy plant, 30 MWth

TOSSILO Spa, owner of the MSW incineration plant in Macomer, appointed W.T.E. to draft the technical and economical prefeasibility study giving:

- the lay out and  the dimensioning of a new incineration plant with 30 MWth capacity, to be built in the area of the existing one, operating with two fluidised bed furnaces;

- grate combustion system providing an yearly average thermal flux of 28 MW.

W.T.E. delivered:

a general lay out,

a preliminary dimensioning of the main sections of the plant and their process

three different solutions of lay out and sections.

 

CLIENT

TOSSILO SPA

LOCATION

Macomer (NU)

COUNTRY

Italy

YEAR

2010

INDUSTRY

Waste to energy plant

OBJECT

Complete System

ACTIVITY

Engineering

ASSIGNMENTS

Pre-feasibility study